Microsoft 70-178 Exam Overview:
| Certification Vendor: | Microsoft |
|---|---|
| Exam Name: | Microsoft Project 2010, Managing Projects |
| Exam Number: | 70-178 |
| Related Certifications: | Microsoft Certified Technology Specialist (MCTS): Microsoft Project 2010 |
| Real Exam Qty: | 40-60 |
| Passing Score: | 700/1000 |
| Exam Duration: | 120-150 |
| Exam Format: | Multiple Choice, Case Studies, Drag and Drop |
| Certificate Validity Period: | Retired (exam discontinued) |
| Exam Price: | USD 165 (varies by region) |
| Available Languages: | English, German, Japanese, Chinese (Simplified), French |
| Sample Questions: | ![]() |
| Exam Way: | Proctored exam delivered via Pearson VUE test centers (historical delivery method) |
| Pre Condition: | Recommended experience using Microsoft Project 2010 and basic project management knowledge |
| Official Syllabus URL: | https://learn.microsoft.com/en-us/credentials/certifications/retired-certifications/ |
Microsoft 70-178 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Customizing Microsoft Project | - Customize views, tables, and fields - Configure project settings and templates |
| Topic 2: Reporting and Communication | - Communicate project status to stakeholders - Generate project reports and dashboards |
| Topic 3: Planning Projects | - Create and configure project plans in Microsoft Project 2010 - Define tasks, dependencies, and milestones - Assign resources and optimize schedules |
| Topic 4: Managing and Tracking Projects | - Manage resource allocation and workload - Track project progress and update schedules - Handle project changes and baselines |
| Topic 5: Initiating Projects | - Define project scope and objectives - Identify stakeholders and project constraints |
70-178 Exam — Answers to Common Questions
Recommended experience using Microsoft Project 2010 and basic project management knowledge Vendor eligibility rules do evolve, so double-check on the official page (official 70-178 exam page) before you pay the fee.
Files first: as an online product, the Microsoft Project 2010, Managing Projects material is obtainable immediately after ordering — an automatic email lands in your mailbox within a minute, with unlimited installations and 24/7 help if nothing shows up within 2 hours. Failure is covered too: take the corresponding 70-178 exam within 60 days of purchase, and if you don't pass, submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam for a full refund processed within 7 days. Exclusions apply — exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products. A free exchange for two equal-value products is the alternative.
Plan on USD 165 (varies by region) per attempt and 700/1000 as the pass mark. Since every retake bills again, rehearse with the 70 practice questions from Test4Cram first — accurate preparation is cheaper than a second registration.
The Microsoft Project 2010, Managing Projects blueprint covers 5 domains — including Initiating Projects, Planning Projects, Reporting and Communication. Treat the weightings as your study budget: heavy domains get heavy hours. The complete outline above lists every subtopic.
120-150, 40-60 questions. Build pace by practicing in short bursts on the Test4Cram APP, then graduate to full timed simulations in the software engine before test day.
Yes — although online products can't be touched, we offer free demos before you really choose. Download the Microsoft Project 2010, Managing Projects trial, judge the question quality yourself, and remember every purchase includes 365 days of free updates (renewable at half price after that).
The Microsoft Project 2010, Managing Projects is Microsoft's exam for the Microsoft Project certification, at the Professional level — formal proof of professional ability that employers can verify. Related credentials include Microsoft Certified Technology Specialist (MCTS): Microsoft Project 2010.
Microsoft Project 2010, Managing Projects Sample Questions:
A section of your project contains only a summary task along with four subtasks and a milestone. You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering. What should you do?
- A. Modify the start and finish dates of the summary task.
- B. Drag the summary task.
- C. Select the summary task and change the scheduling mode to Manually Scheduled.
- D. Select the entire section and click Move Task.
Correct Answer: B 🗳️
You need to import a task list from a Microsoft Office SharePoint 2010 site to create a project schedule in Project 2010. You need to achieve this goal while maintaining SharePoint synchronization. What should you do?
- A. Use the New from SharePoint feature and type the URL that contains the task list.
- B. Use the Save to SharePoint feature and type the URL that contains the task list.
- C. Save the SharePoint task list to a Microsoft Excel file and use the Project Import Wizard.
- D. Open the SharePoint task list in Datasheet view and copy the tasks to a blank project file.
Correct Answer: A 🗳️
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
- A. Create a manually scheduled summary task.
- B. Update the project calendar.
- C. Select the Project Summary Task option.
- D. Select the Summary Tasks option.
Correct Answer: A 🗳️
You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?
- A. Create a base calendar for each shift.
- B. Change the maximum units for each resource.
- C. Create shift resource departments.
- D. Create three tasks, one for each shift.
Correct Answer: A 🗳️
You create a new Gantt Chart view. You need to copy the view to a different project. What should you do?
- A. Use the Organizer tool.
- B. Use the Save Views feature.
- C. Use the Compare Projects feature.
- D. Use the Links Between Projects tool.
Correct Answer: A 🗳️