NEW QUESTION 15
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?

  • A. Cost forecast
  • B. Results analysis
  • C. Easy Cost Planning
  • D. Availability control

Answer: D

 

NEW QUESTION 16
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.

  • A. By searching for the individual status
  • B. By searching via status selection profile
  • C. By searching via status combination code
  • D. By searching for the status profile

Answer: A,D

 

NEW QUESTION 17
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project type
  • B. In the project definition of a standard WBS
  • C. In the project profile
  • D. In the operative WBS element
  • E. In the project version

Answer: B,C,D

 

NEW QUESTION 18
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.

  • A. Goods receipt into unvaluated project stock
  • B. Goods receipt of a non-stock item
  • C. Goods receipt into valuated project stock
  • D. Recording of external services in the service entry sheet

Answer: A,D

 

NEW QUESTION 19
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Basic dates of the network activity
  • B. Forecast dates of the WBS
  • C. Basic dates of the WBS
  • D. Actual dates of the network activity

Answer: A

 

NEW QUESTION 20
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.

  • A. A delivery document type must be configured.
  • B. A sold to party is necessary.
  • C. A shipping point is necessary.
  • D. A sales order must be created in advance.

Answer: B,C

 

NEW QUESTION 21
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

  • A. Cost element report on budget updates
  • B. Structure overview for budgets
  • C. Hierarchical report on budget updates
  • D. Line item report for budgets

Answer: D

 

NEW QUESTION 22
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

  • A. Only capacity requirements
  • B. Backward
  • C. Forward
  • D. Current date

Answer: B

 

NEW QUESTION 23
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Plant
  • B. Company code
  • C. Operating concern
  • D. Sales organization
  • E. Controlling area

Answer: A,B,E

 

NEW QUESTION 24
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

  • A. The table of MRP controllers
  • B. The control key
  • C. The network profile
  • D. The scheduling parameters for the network

Answer: D

 

NEW QUESTION 25
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?

  • A. Top-down
  • B. Strict bottom-up
  • C. Bottom-up
  • D. Free planning

Answer: C

 

NEW QUESTION 26
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

  • A. Planned revenue can be transferred from a sales quotation.
  • B. Planned revenue requires a sales order assigned to a WBS element.
  • C. Actual revenue is posted via a billing plan assigned to a WBS element.
  • D. Actual revenue is posted via a billing document created from a sales order

Answer: A,D

 

NEW QUESTION 27
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Milestones
  • B. Project definition
  • C. Sales order items
  • D. WBS elements

Answer: C,D

 

NEW QUESTION 28
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Data entry profile
  • B. Project profile
  • C. Network profile
  • D. Network type

Answer: A

 

NEW QUESTION 29
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
  • B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
  • C. Earliest dates and latest dates are scheduled by forward scheduling.
  • D. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.

Answer: B

 

NEW QUESTION 30
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Confirmations
  • B. Settlement
  • C. Results analysis
  • D. Progress analysis
  • E. Milestone trend analysis

Answer: B,C,D

 

NEW QUESTION 31
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. None
  • B. Individual overview capacity requirements
  • C. Capacity load work center view
  • D. Structure overview
  • E. Extended capacity evaluation

Answer: B

 

NEW QUESTION 32
Which object is used to allocate the costs from a claim to the project structure?

  • A. Network activity
  • B. Internal order
  • C. Claim
  • D. WBS element

Answer: B

 

NEW QUESTION 33
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • B. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
  • C. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
  • D. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.

Answer: C

 

NEW QUESTION 34
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans enable the billing process to be carried out.
  • B. Billing plans are prerequisites for quotation creation.
  • C. Billing plans are used for revenue planning.
  • D. Billing plans are copied automatically to the sales order item.

Answer: A

 

NEW QUESTION 35
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.

  • A. DIP is used to create a quotation.
  • B. Material determination is mandatory.
  • C. Usage of cost elements is mandatory.
  • D. Sources can be based on line items.
  • E. Sales prices are maintained in the DIP profile.

Answer: A,D,E

 

NEW QUESTION 36
Which planning method can prevent further rescheduling of activities?

  • A. Capacity requirements activation
  • B. Capacity leveling
  • C. Workforce planning
  • D. Partial confirmation of activities

Answer: A

 

NEW QUESTION 37
Which report can use user-specific layouts?

  • A. Cost element report
  • B. Enhanced individual overview
  • C. Line item report
  • D. Hierarchical report

Answer: C

 

NEW QUESTION 38
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

  • A. The activity output price for the activity type and cost center assigned to the work center is not maintained.
  • B. The duration is missing in the activity.
  • C. The formula for costing in the work center is incorrect.
  • D. The Determine Costs indicator in the network header rules out planned cost calculation.
  • E. Integrated planning for the network is active.

Answer: A,B,D

 

NEW QUESTION 39
How can you update the degree of processing for an activity?

  • A. By scheduling the activity
  • B. By changing the activity
  • C. By confirming the activity
  • D. By using results analysis

Answer: C

 

NEW QUESTION 40
......