NEW QUESTION # 43
What does a line hierarchy in repetitive manufacturing represent?
- A. A production line with an alternative sequence in the routing
- B. A production line with prioritized work centers
- C. A production line with a parallel sequence in the routing
- D. A production line with more than one work center
Answer: D
Explanation:
A line hierarchy in repetitive manufacturing represents the structure of a production line that consists of multiple work centers. A line hierarchy is a master data object that defines the sequence and the relationship of the work centers that are involved in producing a material. A line hierarchy can be split into different levels, such as line segments, processing stations, or takt areas, to reflect the complexity and the variability of the production line. A line hierarchy can be used for planning and scheduling operations, controlling material flow, and monitoring production performance12.
The other options are not correct for the following reasons:
A production line with prioritized work centers (B): This is not correct. A line hierarchy does not define the priority of the work centers, but the order and the dependency of the work centers. The priority of the work centers can be determined by other factors, such as the capacity availability, the production rate, or the scheduling parameters.
A production line with a parallel sequence in the routing (C): This is not correct. A line hierarchy does not represent the parallel sequence in the routing, but the linear sequence of the work centers. A parallel sequence in the routing means that two or more operations can be performed simultaneously on different work centers for the same material. A parallel sequence in the routing can be modeled by using alternative sequences or parallel sequences in the line hierarchy3.
A production line with an alternative sequence in the routing (D): This is not correct. A line hierarchy does not represent the alternative sequence in the routing, but the main sequence of the work centers. An alternative sequence in the routing means that there are different options for performing an operation on different work centers for the same material. An alternative sequence in the routing can be modeled by using alternative sequences or parallel sequences in the line hierarchy3.
Reference:
https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/9231f9504a62eb5ee10000000a44538d.html
NEW QUESTION # 44
How would you define pegging in the context of Advanced Planning?
- A. An evaluation to identify material or capacity shortages in the billofmaterial structure after the production planning run
- B. An evaluation that is ordered according to the billofmaterial structure of all related products represents the relationship between the receipt the issue elements
- C. An evaluation that is ordered according to the network structure of all related products represents the coverage of issue elements with receipt elements stock
- D. An evaluation to identify overstock situations in the balance between the receipt the issue elements after the production planning run
Answer: B
NEW QUESTION # 45
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.
- A. Stability
- B. Efficiency
- C. Timeliness
- D. Accuracy
Answer: A,B
NEW QUESTION # 46
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable and physically connected tanks? Note: There are 2 correct answers to this question.
- A. Resource network
- B. Resource matrix
- C. Resource selection
- D. Resource hierarchy
Answer: A,C
Explanation:
A resource network is a business object in PP/DS that defines the allowed directed connections between two or more resources. A directed connection means that the connection from Resource 1 to Resource 2 is not the same as the inverse connection from Resource 2 to Resource 1. You use this object to model existing production constraints more precisely, with the objective of creating a finite and technically feasible production schedule. Resource networks simplify the modeling of resource restrictions for consecutive operations or orders1 A resource selection is a business object in PP/DS that defines the criteria for selecting a suitable resource for an operation or an order. You use this object to specify the characteristics, attributes, and capacities of the resources that can be used for a particular production process. Resource selection allows you to optimize the resource utilization and reduce the setup times and costs2 A resource matrix is a business object in PP/DS that defines the relationships between different resources based on their characteristics and attributes. You use this object to determine the setup times and costs for changing from one resource to another. Resource matrix allows you to model the setup effort and expense more accurately and improve the production efficiency3 A resource hierarchy is a business object in PP/DS that defines the structure and sequence of resources that are used for a production process. You use this object to represent the logical and physical dependencies of the resources and to control the scheduling and sequencing of the operations or orders. Resource hierarchy allows you to model the production flow and capacity more realistically and ensure the technical feasibility of the production plan.
Reference:
Resource Network | SAP Help Portal
Resource Selection | SAP Help Portal
Resource Matrix | SAP Help Portal
[Resource Hierarchy | SAP Help Portal]
NEW QUESTION # 47
where does the system check master data selection settings during the creation of planned orders and production orders?
Note: There are 3 Correct answers to this question.
- A. In the routing
- B. in the work centers
- C. in the MRP controller
- D. in the bill of material (BOM)
- E. in the production version
Answer: A,D,E
Explanation:
The system checks the master data selection settings during the creation of planned orders and production orders in the following places:
In the bill of material (BOM), the system checks the selection ID, which determines which alternative BOM is selected for the material. The selection ID can be maintained in the material master or in the production version.
In the routing, the system checks the selection ID, which determines which alternative routing is selected for the material. The selection ID can be maintained in the material master or in the production version.
In the production version, the system checks the validity period, the lot size, and the selection profile, which determine whether the production version is valid and applicable for the material. The production version combines the BOM and the routing for a material and can be maintained in the material master or in the production version master data. Reference: SAP S/4HANA Manufacturing for Planning & Scheduling - Implementation Guide, page 16; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 75.
NEW QUESTION # 48
Which of the following processes lead to an entry in the MRP planning file? Note: There are 2 correct answers to this question.
- A. Changing the procurement type in the product master
- B. Changing the stock in inventory management
- C. Changing the storage bin in warehouse management
- D. Changing the delivery address in transportation management
Answer: A,B
NEW QUESTION # 49
Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. WBS item
- B. Preliminary item
- C. Variablesize item
- D. Work item
Answer: B,C
NEW QUESTION # 50
Which information is required when you create a product master in SAP S/4HANA?
Note: There are 2 correct answers to this question.
- A. Selection screen for plants
- B. Selection screen for views
- C. Base unit of measure
- D. Product type
Answer: C,D
Explanation:
When you create a product master in SAP S/4HANA, you need to enter values for mandatory fields such as product number, product type, base unit of measure, and description. The product type determines the category of the product, such as material, service, or article. The base unit of measure defines the unit in which you manage the product in all business transactions. The selection screen for views and plants are optional fields that allow you to choose which views and plants you want to maintain for the product master. Reference: Creating Products, Understanding the Concept of Master Data
NEW QUESTION # 51
Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.
- A. Simultaneous
- B. Manual maintenance
- C. First in first out (FIFO)
- D. 100% check
Answer: B,D
NEW QUESTION # 52
You Have a scheduling agreement with a vendor, you want classic MRP to automatically create schedule lines in case of material shortage, what must you do?
Note: there are 2 correct answers to this question.
- A. Set the creation indicator for purchase requisition on the initial screen of the MRP run.
- B. Set the creation indicator for delivery schedule lines on the initial screen the MRP run.
- C. Add the agreement to the source list and mark it for MRP relevance.
- D. Add the agreement to the quota arrangement and mark it for MRP relevance.
Answer: B,C
Explanation:
A scheduling agreement is a long-term agreement with a vendor for the supply of materials or services at predefined dates and quantities. To enable classic MRP to automatically create schedule lines in case of material shortage, you must do the following:
Add the agreement to the source list and mark it for MRP relevance. The source list is a list of possible sources of supply for a material, such as vendors, contracts, or scheduling agreements. By adding the agreement to the source list and setting the MRP indicator, you specify that the agreement is a valid and preferred source of supply for the material.
Set the creation indicator for delivery schedule lines on the initial screen of the MRP run. The creation indicator determines whether the MRP run creates procurement proposals, such as purchase requisitions, planned orders, or delivery schedule lines. By setting the creation indicator for delivery schedule lines, you instruct the MRP run to create schedule lines for the scheduling agreement, based on the material requirements and the agreement conditions.
Adding the agreement to the quota arrangement and marking it for MRP relevance is not necessary, as the quota arrangement is used to distribute the total requirements of a material among several sources of supply. Setting the creation indicator for purchase requisition on the initial screen of the MRP run is not correct, as the purchase requisition is a different type of procurement proposal than the delivery schedule line. Reference: Scheduling Agreement | SAP Help Portal, Source List | SAP Help Portal, MRP Run | SAP Help Portal.
NEW QUESTION # 53
Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.
- A. You can use mass processing to set production orders to technically complete.
- B. You can use mass processing to read PP master data for production orders.
- C. You can use trigger points to automatically create rework orders via confirmations.
- D. You can use the production scheduling profile to automatically set orders to technically complete.
Answer: A,C
NEW QUESTION # 54
How are dependent requirements for assemblies created?
Note: There are 2 correct answers to this question.
- A. They are created with exact times in Advanced Planning.
- B. They are only created for multilevel bill of material (BOM) structures.
- C. They are created together with the independent requirement for the finished product.
- D. They are created on assembly level during the planning run.
Answer: A,D
NEW QUESTION # 55
What could be the reason for different combinations of components in a multiple bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Lot size
- B. Manufacturing date
- C. BOM component status
- D. BOM header status
Answer: A,B
NEW QUESTION # 56
What are some benefits of planning with planned independent requirements for finished materials? Note: There are 2 correct answers to this question.
- A. Reduced times for final assembly
- B. Option to use maketoorder production
- C. Reduced delivery times
- D. Option to forecast planning for production resources
Answer: A,C
NEW QUESTION # 57
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. Orders (dispatched) chart
- B. Capacity requirements chart
- C. Order (pool) chart
- D. Work center capacities chart
Answer: B,D
NEW QUESTION # 58
What are some SAP recommended guiding principles to achieve clean core operations?
Note: There are 3 correct answers to this question.
- A. Establish an organizational structure technical foundation transformation methodology for clean core.
- B. Integrate clean core practices in the endtoend value process chain.
- C. Establish release management.
- D. Define roles responsibilities as part of a process transformation office.
- E. Establish regular housekeeping tasks procedures.
Answer: A,C,D
NEW QUESTION # 59
How can you achieve a feasible production plan in case of capacity constraints?
Note: There are 3 correct answers to this question.
- A. Reduce the planning time interval.
- B. Determine a time period with available capacity on the planning board.
- C. Form optimum sequences to reduce setup times.
- D. Increase the capacity supply in a timephased interval.
- E. Execute an infinite production planning run for the critical resources.
Answer: B,C,D
NEW QUESTION # 60
......
SAP C-TS422-2023 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
| Topic 7 |
|
| Topic 8 |
|
| Topic 9 |
|
Updated Jan-2025 Pass C-TS422-2023 Exam - Real Practice Test Questions: https://www.test4cram.com/C-TS422-2023_real-exam-dumps.html
Pass Your Exam With 100% Verified C-TS422-2023 Exam Questions: https://drive.google.com/open?id=1hKcEooP6NMKW2rUYp5uU09oyw0kRSIzl