NEW QUESTION 85
you want to set up integrated planning for your internal orders. What do you need to do ? 2 Answers
- A. Set the relevant indicator in the internal order master record
- B. Set therelevant indicator in the controlling area
- C. Set the relevant indicator in the planning profile of the order type
- D. Set the relevant indicator in the CO version
Answer: A,D
NEW QUESTION 86
How can you populate local variables in Profitability Analysis reports?
- A. By user exit
- B. By business Add-in
- C. Byuser entry during report execution
- D. By populating from user parameters
Answer: C
NEW QUESTION 87
How can you configure cycles for period-end allocation?
There are TWO correct answers for this question
Response:
- A. Create cycles that iterate with each other
- B. Define allocation for the same cost center in multiple segments
- C. Use different allocation rules within one segment
- D. Assign several segments to a cycle
Answer: B,D
NEW QUESTION 88
In which SAP S/4HANA components can you analyze the results of the results analysis?
There are 3 correct answers to this question.
Response:
- A. Sales and distribution
- B. Financial accounting
- C. Profitability analysis
- D. Inventory management
- E. Profit center accounting
Answer: B,C,E
NEW QUESTION 89
Which are levels of internal order planning? There are TWO correctanswers for this question
- A. Integrated planning
- B. Group costing
- C. Overall planning
- D. Primary and secondary cost and revenue planning
Answer: A,C
NEW QUESTION 90
When you create a planning layout, which objects can you use to define the data columns?
There are THREE correct answers for this question
Response:
- A. Summarization level
- B. Distribution key
- C. Formulas
- D. Value fields
- E. Characteristics
Answer: C,D,E
NEW QUESTION 91
How can you configure cycles forperiod-end allocation? There are TWO correct answers for this question
- A. Create cycles that iterate with each other
- B. Define allocation for the same cost center in multiple segments
- C. Use different allocation rules within one segment
- D. Assign several segments to a cycle
Answer: B,D
NEW QUESTION 92
You enter the actual activity quality for work and vacation in the cross-application time sheet.
Which options can you choose in the master data of the activity type to ensure the quantities and values are posted in Management Accounting?
There are TWO correct answers for this question
Response:
- A. Manual entry, indirect allocation
- B. Manual entry, manual allocation
- C. Manual entry, no allocation
- D. Indirect determination, indirect allocation
Answer: B,C
NEW QUESTION 93
Which currency types can you use for costing-based CO-PA?
There are TWO correct answers for this question
Response:
- A. Operating concern currency
- B. Group currency
- C. Company code currency
- D. Controlling area currency
Answer: A,C
NEW QUESTION 94
To which objects do you assign the elements of the cost component split to ensure the transfer of costing to costing-based CO-PA?
- A. G/L accounts
- B. Segments
- C. Controling Area
- D. Value fields
Answer: D
NEW QUESTION 95
You use a production order with product Cost by period and you entered a result analysis key and variance key. How does the system calculate variances in product Cost by Period ?
- A. Variances = Target costs - Delivery value
- B. Variances = Actual costs - Delivery value
- C. Variances = Target costs - Delivery value - WIP
- D. Variances = Actual costs - Delivery value - WIP
Answer: D
NEW QUESTION 96
What does the calculation of a condition type in the costing sheet depend on? There are 2 correct answers to this question.
- A. Segment
- B. Valuation
- C. Calculation type
- D. Condition class
Answer: C,D
NEW QUESTION 97
On which document in the sales process is the profit center initially entered?
Response:
- A. Service contract
- B. Sales inquiry
- C. Sales order
- D. Goods issue
Answer: C
NEW QUESTION 98
You configured an overhead costing sheet that uses the quantity-based overhead approach to calculate the overhead amount. What is required for the amount to be calculated?
- A. Settlement rules with valid receiver objects
- B. Statistically figures with values for the period
- C. Activity types with actual or plan quantities maintained
- D. Cost accounts with the option to record quantity
Answer: C
NEW QUESTION 99
What can you analyze in detail when you transfer the cost component split from product cost planning to costing-based CO-PA?
Response:
- A. Cost of goods sold
- B. Variance categories
- C. Cost of goods manufactured
- D. Sales revenues
Answer: A
NEW QUESTION 100
How does the system derive the requirement type from the material master data ?
- A. MRP group -> strategy group -> planning strategy -> requirements type
- B. Strategy group -> planning strategy -> requirements type
- C. Strategy group -> planning strategy -> requirements class -> requirements type
- D. MRP group requirements class -> planning strategy -> requirements type
Answer: A,B
NEW QUESTION 101
You want to run an assessment cycle in Profitability Analysis to allocate cost centers costs during period-end closing for your organization. Which of the following objects is part of the assessment cycle?
- A. Template
- B. PA transfer structure
- C. Cycle iteration
- D. Tracing factor
Answer: D
NEW QUESTION 102
What can you configure in the settlement profile?
- A. Determine whether settlement is required
- B. Determine an overhead key
- C. Define document management parameters
- D. Define a number range for settlement documents
Answer: A,C
NEW QUESTION 103
Duringposting, from which object does the system first derive the profit center if the profit center is NOT directly assigned to a network activity?
- A. Project definition
- B. Network header
- C. WBS element
- D. Dummy profit center
Answer: B
NEW QUESTION 104
For which objects can you revaluate activities and business processes at actual prices?
There are THREE correct answers for this question
Response:
- A. Cost centers
- B. Work breakdown structure elements
- C. Profitability segments
- D. Profit centers
- E. Work centers
Answer: B,C,D
NEW QUESTION 105
You want to use a template for activity and process assignment to your material cost estimate. What do you need to do ?
- A. Assign a template directly to costing view 1 of the material master record
- B. Use the costing sheet of the costind view 1 in the template determination table
- C. Use the template allocation function in the material cost estimate and the costing run
- D. Assign a template to an operation in the routing of the material
Answer: C
NEW QUESTION 106
......
C_TS4CO_1909 Dumps PDF - C_TS4CO_1909 Real Exam Questions Answers: https://www.test4cram.com/C_TS4CO_1909_real-exam-dumps.html