Commutes, flights, dead Wi-Fi zones — the ASIS Physical Security Professional engines from Test4Cram don't care. Practice offline once the PSP content is on your device, then let the auto-graded mock tests through the 218 questions tell you exactly where you stand.
ASIS PSP Exam Overview:
| Certification Vendor: | ASIS International |
|---|---|
| Exam Name: | ASIS Physical Security Professional (PSP) Certification Exam |
| Exam Number: | PSP |
| Exam Format: | Multiple-choice (single best answer) |
| Related Certifications: | Associate Protection Professional (APP) Certified Protection Professional (CPP) Professional Certified Investigator (PCI) |
| Available Languages: | English |
| Real Exam Qty: | 140 questions (125 scored + 15 unscored pretest items) |
| Certificate Validity Period: | 3 years (renewal required via continuing professional education) |
| Passing Score: | Scaled score 650 (on ASIS 100–900 scale) |
| Exam Duration: | 150 minutes |
| Exam Price: | $300–$485 USD (member/non-member varies by region and registration type) |
| Recommended Training: | ASIS PSP Certification Preparation Resources |
| Exam Registration: | ASIS Certification Handbook ASIS PSP Certification Page |
| Sample Questions: | ![]() |
| Exam Way: | Computer-based testing at Pearson VUE test centers and authorized online proctoring (availability varies by region) |
| Pre Condition: | Typically requires 4 years experience in physical security with a bachelor's degree OR 6 years experience without a degree, plus full-time employment in a security-related role |
| Official Syllabus URL: | https://www.asisonline.org/certification/physical-security-professional/ |
ASIS PSP Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Implementation of Physical Security Measures | - Operational effectiveness
|
| Topic 2: Physical Security Assessment | - Risk and threat assessment fundamentals
|
| Topic 3: Application, Design, and Integration of Physical Security Systems | - Technology integration
|
ASIS PSP Exam: Your Questions, Answered
Head to the vendor's official registration channels:
One detail worth checking at booking: the PSP exam runs Computer-based testing at Pearson VUE test centers and authorized online proctoring (availability varies by region), so choose the format you are most comfortable with.
The vendor officially recommends:
Take the courses for the theory, then switch to measurement: the PSP practice questions from Test4Cram — with auto-graded mock tests — show you what is actually sticking.
You're looking at 140 questions (125 scored + 15 unscored pretest items) questions in 150 minutes. Do the math early, not in the exam room: decide your per-question pace, practice skipping hard items without panic, and finish at least two full timed mock tests — the Test4Cram engine grades them automatically in about a minute, so you get instant feedback on where your time goes.
Delivery is the easy part: pay, click the email link that arrives within a minute, and the PSP files download in about a minute — no extra software, no installation limits. If 2 hours pass with nothing, our support team will fix it. The refund side runs on clear rules: take the corresponding PSP exam within 60 days of purchase, and if you fail, submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam for a 100% refund, processed within 7 days. Exams sat within 3 days of purchase don't qualify, candidate and payer names must match, and free or expired products are excluded. Prefer an exchange? Take two equal-value exam products free of charge and keep your original updates.
You need Scaled score 650 (on ASIS 100–900 scale) to pass, and registration costs $300–$485 USD (member/non-member varies by region and registration type) at the official rate. One uncomfortable truth: the fee is per attempt, so a fail means paying it again. Candidates who self-test first — with auto-graded mock exams built from the 218 questions at Test4Cram — tend to pay that fee exactly once.
The vendor's blueprint for the ASIS Physical Security Professional has 3 domains, led by Application, Design, and Integration of Physical Security Systems, Implementation of Physical Security Measures, Physical Security Assessment. The weighting is a study plan in disguise — heavy domains deserve heavy hours. You'll find every domain and subtopic in the complete outline above.
Passing the PSP exam earns the Physical Security Professional (PSP) certification — a Professional-level credential — issued directly by ASIS. It is proof of ability that travels well across employers and borders. The credential also links to Certified Protection Professional (CPP), Professional Certified Investigator (PCI), Associate Protection Professional (APP), so it can be a first step rather than a final destination.
Yes — the free PDF demo shows the real question quality before any payment. And the value continues after purchase: 365 days of free updates come standard, with a 50% renewal discount if your update period ever expires.
Typically requires 4 years experience in physical security with a bachelor's degree OR 6 years experience without a degree, plus full-time employment in a security-related role These rules do get revised, so before you book, double-check the current requirements on the official PSP exam page — what the vendor publishes is what counts.
ASIS Physical Security Professional Sample Questions:
What changes to logic would eliminate Activity B from the critical path?
- A. Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO
- B. Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0
- C. Replace the relationship from Activity B to Activity C with SSO
- D. Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C
Correct Answer: D 🗳️
Explanation: Only visible for Test4Cram members. You can sign-up / login (it's free).
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
- B. It doesn't account for interdependent between activities.
- C. It requires a backward pass to calculate late dates.
- D. It assumes that resources are unlimited.
Correct Answer: D 🗳️
Explanation: Only visible for Test4Cram members. You can sign-up / login (it's free).
Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?
- A. Delay due to labor shortage
- B. Cost overruns due to cement shortage
- C. Liquidated damages on the SDOT contract
- D. Delay due to SDOT's other projects
Correct Answer: D 🗳️
Explanation: Only visible for Test4Cram members. You can sign-up / login (it's free).
Background
Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.
It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.
You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.
With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.
In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.
1. Pull the project team together and ensure everyone understands which activities are on the critical path.
Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.
2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.
3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.
4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.
Assignment
Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:
a. the current problem and potential impact(s);
b. each course of action, stating advantages and disadvantages as appropriate; c. your recommendations, properly supported.
Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).
While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.
Take time to read the problem and consider what you want Evan to say. Good luck!
Correct Answer:
See the Explanation for complete Solution for this.
Explanation:
To: Desmond Rayburn, Director of Information Services
From: Evan Marshal, Corporate Scheduler
Date: [Insert Current Date]
Subject: Mitigation Plan for Project JP-114 Delays
Current Problem and Potential Impacts
Project JP-114 has experienced schedule delays and cost overruns. The project has expended $37,000 against a planned budget of $30,000 to date, exceeding the planned budget by 23%. Additionally, productivity issues have impacted critical path activities, further delaying progress. With nine months remaining, failing to address these issues could result in penalties, further cost increases, and client dissatisfaction.
Courses of Action
* Focus Existing Team on Critical Path with Periodic Overtime
* Advantages: Uses team familiarity; incurs a moderate budget increase (20%).
* Disadvantages: Risks resource strain and potential burnout if overtime is prolonged.
* Outsource Work to Consultants
* Advantages: Accelerates schedule by parallel work streams; minimizes internal team overtime.
* Disadvantages: Higher budget impact (up to 40%); requires effective integration of external deliverables.
* Mandatory Overtime (50-Hour Work Week)
* Advantages: Ensures rapid progress across the project.
* Disadvantages: Extremely high cost (60% increase); risks significant employee fatigue and declining morale.
* Continue as Is and Accept Late Delivery Penalties
* Advantages: No immediate resource strain.
* Disadvantages: Significant penalties (50% budget increase); damages stakeholder confidence and corporate reputation.
Recommendation
I recommend Option 1, combined with selective outsourcing (Option 2), to achieve the best balance of cost control and schedule recovery.
* Focus the internal team on critical path activities with targeted use of periodic overtime. This ensures efficient allocation of resources and minimizes strain while addressing the most urgent delays.
* Outsource select non-critical tasks to experienced consultants. This parallel effort reduces the workload on the internal team, limits overtime, and accelerates overall progress.
Rationale:
This hybrid approach keeps the budget increase to approximately 30-35% while effectively addressing schedule delays. It balances cost efficiency, resource management, and stakeholder satisfaction. Proper coordination will ensure smooth integration between internal and external teams.
Conclusion
This plan provides the most feasible path to bringing Project JP-114 back on track. It mitigates risks of extended delays while maintaining budget discipline. I am available for further discussions to outline a detailed implementation plan.
Best Regards,
Evan Marshal
Corporate Scheduler
What is the remaining work duration of Active D?
- A. 4.
- B. 11
- C. 8.
- D. 3.
Correct Answer: C 🗳️